Site Upgrade Version 2 is lamost out ..Takenote of that County Director Confirms June 2026 Project Review Schedule Beneficiary Verification Desk Opens At Kitale Huduma Centre Public Viewing Register Updated For Trans-Nzoia AHP Sites Community Baraza Dates Published For Saboti And Kiminini Affordable Housing Tracker Maintenance Window Announced Official Progress Note Released For Maili Tatu Estate Governor Issues Statement on Beneficiary Selection and Allocation Criteria Site Upgrade Version 2 is lamost out ..Takenote of that County Director Confirms June 2026 Project Review Schedule Beneficiary Verification Desk Opens At Kitale Huduma Centre Public Viewing Register Updated For Trans-Nzoia AHP Sites Community Baraza Dates Published For Saboti And Kiminini Affordable Housing Tracker Maintenance Window Announced Official Progress Note Released For Maili Tatu Estate Governor Issues Statement on Beneficiary Selection and Allocation Criteria
Active Saboti Started Q1 2024 Est. Delivery Q1 2026

Maili Tatu Affordable Housing Estate

Matisi, Saboti Superstructure walls and openings Kitale Build Contractors Ltd
67% Project Progress
Units Planned 1,040
Ward Matisi
Contractor Kitale Build Contractors Ltd
Funding Source National AHP Fund
Start Date Q1 2024
Est. Delivery Q1 2026

Project Overview

Flagship affordable housing estate in the Kitale urban growth area, planned as a mixed-typology residential development for low-to-middle-income applicants registered through Boma Yangu.

Lead AgencyState Dept. of Housing
Site EngineerEng. S. K. Kariuki
FundingNational AHP Fund
Current Activity: Superstructure walls and openings

Live Progress Tracker

Overall Progress 67%

Data updated regularly by the Trans-Nzoia County project delivery team.

1,040Units Planned
697Units In Progress
Q1 2026Target Delivery
60%Programme Progress
6Completed Tasks
4Needs Attention

Project Timeline

15 Jan 2024

Programme Announcement

10 Feb 2024

Site Selection & Survey

5 Sep 2024

Foundation Works

31 Aug 2025

Structural Frame CURRENT