Site Upgrade Version 2 is lamost out ..Takenote of that County Director Confirms June 2026 Project Review Schedule Beneficiary Verification Desk Opens At Kitale Huduma Centre Public Viewing Register Updated For Trans-Nzoia AHP Sites Community Baraza Dates Published For Saboti And Kiminini Affordable Housing Tracker Maintenance Window Announced Official Progress Note Released For Maili Tatu Estate Governor Issues Statement on Beneficiary Selection and Allocation Criteria Site Upgrade Version 2 is lamost out ..Takenote of that County Director Confirms June 2026 Project Review Schedule Beneficiary Verification Desk Opens At Kitale Huduma Centre Public Viewing Register Updated For Trans-Nzoia AHP Sites Community Baraza Dates Published For Saboti And Kiminini Affordable Housing Tracker Maintenance Window Announced Official Progress Note Released For Maili Tatu Estate Governor Issues Statement on Beneficiary Selection and Allocation Criteria
Active Saboti Started Q3 2024 Est. Delivery Q2 2026

Kitale Polytechnic Institutional Housing

Tuwani, Saboti Foundation works and service ducting EduBuild Contractors Ltd
25% Project Progress
Units Planned 96
Ward Tuwani
Contractor EduBuild Contractors Ltd
Funding Source Institutional Housing Programme
Start Date Q3 2024
Est. Delivery Q2 2026

Project Overview

Institutional housing project supporting staff and learner accommodation needs around Kitale Polytechnic and the wider Kitale education corridor.

Lead AgencyState Dept. of Housing
Site EngineerEng. A. K. Njoroge
FundingInstitutional Housing Programme
Current Activity: Foundation works and service ducting

Live Progress Tracker

Overall Progress 25%

Data updated regularly by the Trans-Nzoia County project delivery team.

96Units Planned
24Units In Progress
Q2 2026Target Delivery
25%Programme Progress
2Completed Tasks
8Needs Attention

Project Timeline

5 Nov 2024

Site Preparation

30 Jun 2025

Foundation Works CURRENT