Active
Endebess
Started Q2 2024
Est. Delivery Q2 2026
Suam Border Post Affordable Housing Estate
35%
Project Progress
Units Planned
150
Ward
Chepchoina
Contractor
Frontier Housing Ltd
Funding Source
National AHP Fund
Start Date
Q2 2024
Est. Delivery
Q2 2026
About This Project
Project Overview
Affordable housing estate serving the Suam border corridor, designed to support workers, traders, and households around the expanding cross-border economy.
Current Activity: Superstructure walls and openings
Project Progress
Live Progress Tracker
150Units Planned
53Units In Progress
Q2 2026Target Delivery
28%Programme Progress
2Completed Tasks
8Needs Attention
Key Milestones
Project Timeline
20 May 2024
Site Mobilisation
28 Feb 2025
Substructure Works CURRENT
Site Photography