Active
Kiminini
Started Q2 2024
Est. Delivery Q4 2025
Kiminini Modern Market
42%
Project Progress
Stalls Planned
180
Ward
Kiminini
Contractor
Kiminini Urban Works Ltd
Funding Source
County Development Budget
Start Date
Q2 2024
Est. Delivery
Q4 2025
About This Project
Project Overview
Market infrastructure project for Kiminini town, planned to improve trader space, public hygiene, customer circulation, and local revenue collection.
Current Activity: Superstructure walls and openings
Project Progress
Live Progress Tracker
180Stalls Planned
76Stalls In Progress
Q4 2025Target Delivery
35%Programme Progress
3Completed Tasks
7Needs Attention
Key Milestones
Project Timeline
15 Jun 2024
Site Handover
30 Apr 2025
Ground Floor Works CURRENT