Site Upgrade Version 2 is lamost out ..Takenote of that County Director Confirms June 2026 Project Review Schedule Beneficiary Verification Desk Opens At Kitale Huduma Centre Public Viewing Register Updated For Trans-Nzoia AHP Sites Community Baraza Dates Published For Saboti And Kiminini Affordable Housing Tracker Maintenance Window Announced Official Progress Note Released For Maili Tatu Estate Governor Issues Statement on Beneficiary Selection and Allocation Criteria Site Upgrade Version 2 is lamost out ..Takenote of that County Director Confirms June 2026 Project Review Schedule Beneficiary Verification Desk Opens At Kitale Huduma Centre Public Viewing Register Updated For Trans-Nzoia AHP Sites Community Baraza Dates Published For Saboti And Kiminini Affordable Housing Tracker Maintenance Window Announced Official Progress Note Released For Maili Tatu Estate Governor Issues Statement on Beneficiary Selection and Allocation Criteria
Active Kiminini Started Q2 2024 Est. Delivery Q4 2025

Kiminini Modern Market

Kiminini, Kiminini Superstructure walls and openings Kiminini Urban Works Ltd
42% Project Progress
Stalls Planned 180
Ward Kiminini
Contractor Kiminini Urban Works Ltd
Funding Source County Development Budget
Start Date Q2 2024
Est. Delivery Q4 2025

Project Overview

Market infrastructure project for Kiminini town, planned to improve trader space, public hygiene, customer circulation, and local revenue collection.

Lead AgencyTrans-Nzoia County Government
Site EngineerEng. L. Chebet
FundingCounty Development Budget
Current Activity: Superstructure walls and openings

Live Progress Tracker

Overall Progress 42%

Data updated regularly by the Trans-Nzoia County project delivery team.

180Stalls Planned
76Stalls In Progress
Q4 2025Target Delivery
35%Programme Progress
3Completed Tasks
7Needs Attention

Project Timeline

15 Jun 2024

Site Handover

30 Apr 2025

Ground Floor Works CURRENT